Hva betyr 979 ?

A communication error exists between the Fronius Symo Hybrid inverter and the Fronius Solar Battery. Battery operation is not possible, and grid feed-in resumes. This code is displayed if not in standby mode.

Vanlige årsaker

  • Loose or damaged communication wiring between the inverter and battery
  • Faulty communication interface on either device

Reparasjonssteg & Sjekkliste

Klikk på steg for å spore fremgangen.

  1. 1

    If the system is not in standby mode, check the communication wiring between the Fronius Symo Hybrid inverter and the Fronius Solar Battery