Traduciendo...
24594

Equipment Phase Unscheduled or Inhibited

Allen-Bradley · Logix 5000 Advanced Process Control and Drives

¿Qué significa 24594 ?

The PATT instruction cannot take ownership of the equipment phase because it is currently in an unscheduled or inhibited state, or the task containing the equipment phase is inhibited.

Causas comunes

  • The operational state of the equipment phase or its controlling task is preventing ownership acquisition.

Pasos de reparación & Lista de verificación

Haga clic en los pasos para seguir su progreso.

  1. 1

    Verify the scheduling and inhibition status of the equipment phase — ensure it is scheduled and not in an inhibited state.

  2. 2

    Check the status of the controller task containing the equipment phase — confirm the task itself is enabled and not inhibited.

Ver todos los códigos en este manual (19)
Datos técnicos verificados. Última actualización: March 2026

Fallas relacionadas

Fuente: Allen-Bradley Logix 5000 Advanced Process Control and Drives